PDRI for Buildings

Where is PDRI for Buildings used?

The PDRI for Buildings template is used to assess scope definition for building or commercial construction projects.


Key Characteristics

Characteristic Building
Primary Designer Civil Engineer
Project Orientation Vertical
System Node
Utilization Functional Use
Operational Nodal terminations
Interace with Public Moderate
Environmental Impact Moderate
Primary Cost  Building & related systems
Installed Equipment Cost Moderate
Land Cost Variable 
Jurisdiction Interface Moderate

 


Types of Projects

Hotels and motels Stores and Shopping Centres Apartments
Light Assembly and Manufacturing Research and Laboratory Facilities Recreational and Athletic Facilities
Performance Halls Medical Facilities Airport Terminals
Industrial Control Buildings Institutional Buildings Warehouses

 


Project Performance Impact

Application of the PDRI for Buildings template has been tested by the Construction Industry Institute (CII) on billions of dollars worth of building projects.  These projects included office, control buildings, recreation, institutional, and research facilities.

The table below compares project performance using their PDRI score at the time of project authorization (end of detailed scope). Projects with a PDRI score under 200 (a lower score indicates a better defined scope) consistently outperform projects with a PDRI score above 200 in terms of cost, schedule, and change orders.

Performance PDRI Score < 200 PDRI Score > 200 Difference
Cost 3% above budget 9% above budged 6%
Schedule 5% behind schedule 21% behind schedule 16%
Change Orders 8% of budget 11% of budget 3%

Reference: Project Definition Rating Index Building Projects, Implementation Resources 155-2, Version 4.0, Construction Industry Institute, 2013.

Top Ten Elements